The 425 MW Nandipur Power Project would be fully operationalized shortly.

In an interview, Managing Director Nadipur project, Mohammad Mehmood said three units of the plant had already been commissioned and the plant was supplying 300 MW to the national grid station.

Mehmood that fourth unit of combine circle would be ready in few weeks.

To a question, Muhammad Mehmood said the project was completed within its estimated approved PC-1 cost of fifty-eighty billion rupees.

Mehmood said that the Nandipur power plant was 2nd most efficient thermal power plant after Guddu 747 MW.